Industrial Design Protection in South Africa - Filing, Examination, and Maintenance

South Africa offers a structured and efficient system for protecting industrial designs, governed by the Companies and Intellectual Property Commission (CIPC). Understanding the procedural and documentary requirements is essential for applicants seeking design protection under South African law. This article provides a concise overview of the filing process, examination system, protection terms, and maintenance obligations for industrial designs in South Africa.

Authority:
Terms of Protection:
  • For Aesthetic designs: 15 years from the filing date or the earliest priority date.
  • For Functional designs: 10 years from the filing date or the earliest priority date.
Filing Deadline: 
  • For applications claiming Paris Convention priority, the filing must occur within 6 months of the earliest priority date. (South Africa is not a member of the African Regional Intellectual Property Organization (ARIPO) or the African Intellectual Property Organization (OAPI).
Filing Requirements:
  • Representations / Pictures
  • Definitive or descriptive statement
  • Power of Attorney and Declaration (Form P3)
  • Certified copy of priority document (DAS not accepted)
  • Deed of Assignment
  • Locarno Classification Number

If there are two joint applicants and the invention was partially contributed by employees or inventors of both parties, each inventor must cross-assign rights to both applicants. 

The signing dates on Forms P3 and P26 must postdate the effective date of any documents proving the applicant’s entitlement or authorization to apply for the design. Additionally, a Biological and Heritage Resource Declaration is a mandatory submission for design applications. 

Process & Procedure:

CIPC conducts formality examination only for industrial design patent applications. Once all documents are complete, the formal examination is carried out within six months after filing. Applicants must indicate the Locarno Classification number in the application form. According to South African Design Law, multiple embodiments of a single design cannot be filed within one application — each embodiment must be submitted as a separate application.

Grace Period for Novelty:

Designs benefit from a 6-month grace period prior to the filing or priority date.

Grant and Renewal Maintenance Fee: 
  • There are no grant fees for industrial designs in South Africa.
  • The 1st maintenance fee must be paid within 3 years from the filing date. Late payment is allowed within 6 months after the due date with an applicable surcharge. Applicants may pay renewal fees for multiple years at once.
  • Applicants may also request deferred registration, extending the grant period up to 18 months from the filing date, with the option to request another extension.
Granting Time:

The average registration time for an industrial design is 6 - 8 months, depending on the completeness of the submission and CIPC’s examination queue.

Conclusion

South Africa’s industrial design system emphasizes procedural clarity and administrative efficiency. With formal examination as the only review stage and flexible renewal options, the system provides a streamlined pathway for applicants to secure design rights swiftly. Applicants should ensure timely submission of all mandatory forms and supporting documents to avoid delays and maintain continuous protection.